dc.description | MUCEET 2009 is organized by Malaysian Technical Universities Network (MTUN) comprising of Universiti Malaysia Perlis (UniMAP), Universiti Tun Hussein Onn (UTHM), Universiti Teknikal Melaka (UTeM) and Universiti Malaysia Pahang (UMP), 20th - 22nd June 2009 at M. S. Garden Hotel, Kuantan, Pahang. | en_US |
dc.description.abstract | The construction industry is
a major catalyst to the growth of the nation’s
socio economic development. The frequent
delay of the large construction project has been
a phenomenon and it effects the
implementation of the strategic planning. This
paper presents the findings of survey of
dominant cause of delay in large MARA
(Majlis Amanah Rakyat) construction project
in the perspective of project management
consultants (PMC). Respondents of this survey
were personnel that work as PMC ranging from
the executives, managerial and supporting
groups. The result revealed that the five most
significant delay causes as seen by PMC were
cash flow and financial difficulties faced by
contractors, contractor's poor site management,
inadequate contractor experience, shortage of
site workers and ineffective planning and
scheduling by contractors. Hopefully, the
findings of this study will at least shade some
lights to the problems faced by MARA large
construction project and effort can be taken to
improve it. | en_US |
dc.language.iso | en | en_US |
dc.publisher | Universiti Malaysia Pahang (UMP) | en_US |
dc.relation.ispartofseries | Proceedings of the Malaysian Technical Universities Conference on Engineering and Technology (MUCEET) 2009 | en_US |
dc.subject | MUCEET | en_US |
dc.subject | Malaysian Technical Universities Conference on Engineering and Technology | en_US |
dc.subject | Construction delay | en_US |
dc.subject | MARA construction project | en_US |
dc.title | Delay in large MARA construction projects based on project management consultant perspective | en_US |
dc.type | Working Paper | en_US |